New England Highway Belford to Golden Highway.

New England Highway upgrade between Belford and the Golden Highway

Transport for NSW is upgrading the New England Highway between Belford and the Golden Highway to provide two travel lanes in each direction and a flyover for vehicles turning right from the Golden Highway towards Maitland and Newcastle. The NSW Government has announced $97 million for the upgrade to improve traffic flow, travel times and safety for motorists.

Latest news

JUL 2021

JUL 2021Site compound and start of construction

Transport for NSW has engaged Acciona Construction Australia Pty Ltd to deliver the upgrade.

Work to set up a site compound and other site preparation activities will start in early August. Following this, the main project work is expected to start in late August 2021.

For more information on these work activities please view our July 2021 project update (PDF, 538Kb).

Project information

The New England Highway is part of the inland route of the Sydney to Brisbane National Land Transport Network and the primary route connecting the Upper Hunter with Maitland and Newcastle. The Golden Highway connects the New England Highway at Whittingham with Dubbo.

These road corridors are designated B-Double routes and are used extensively by heavy vehicles servicing coal mining, grain production and other industries in the Hunter Valley and the Central West to access the port of Newcastle.

The New England Highway is a critical connection between the urban and employment centres of Maitland and Singleton, which are planned future growth areas for the Hunter region.

Around 22,000 vehicles travel along the New England Highway between Belford and the Golden Highway each day. This section of the New England Highway is currently two lanes westbound and one lane eastbound and has a history of crashes, particularly near the Golden Highway intersection.

The upgrade includes:

  • widening the New England Highway to provide a divided road with two lanes in each direction between Belford and the Golden Highway.
  • replacing the existing right turn movement from the Golden Highway to the New England Highway with a flyover
  • a roundabout on the Golden Highway with a connection to the New England Highway improves safety for motorists turning left onto the New England Highway towards Singleton and provides safer access to adjoining properties.

The upgrade will:

  • increase capacity and connectivity of the New England Highway and Golden Highway for the efficient and reliable movement of freight
  • improve safety at the New England Highway and Golden Highway intersection by reducing the risk of crashes, particularly for motorists turning right from the Golden Highway
  • increase capacity at the New England Highway and Golden Highway intersection to cater for the predicted increase in traffic movements due to future growth in the Hunter
  • allow for access to existing and future adjoining land uses.

The Whittingham rest area adjacent to the New England Highway and Golden Highway intersection was permanently closed on Monday 3 February 2020 as part of the early work for the upgrade.

The nearby townships of Singleton and Branxton offer motorists an alternate place to stop with a range of amenities. Alternative rest areas are located:

  • about 15 kilometres north on the New England Highway at Rixs Creek Road, north of Singleton
  • about 10 kilometres south on the Hunter Expressway at Branxton (heavy vehicles only)
  • about 40 kilometres south on the Hunter Expressway at Buchanan.

 For information about nearby rest area locations and facilities please visit rms.nsw.gov.au/restareas.

Work on the main project is expected to start in late August 2021 and take about three years to complete, weather permitting.

We will continue to keep stakeholders and the community informed as the project progresses.

Project documents

Project updates

Show filesHide files
File Title Size
July 2021 project update

Site compound and start of construction.

538Kb
June 2021 project update

Construction contract awarded

159Kb
December 2019 project update

Whittingham rest area permanently closing on Monday 3 February 2020.

180Kb
September 2019 project update

New England Highway upgrade between Belford and the Golden Highway.

1.2Mb
August 2018 project update

New England Highway upgrade between Belford and the Golden Highway.

91.04Kb
April 2018 project update

New England Highway upgrade between Belford and the Golden Highway - design improvements.

297Kb
June 2017 project update

New England Highway upgrade between Belford and the Golden Highway - concept design and environmental assessment.

5.06Mb
September 2016 project update

New England Highway upgrade between Belford and the Golden Highway.

815Kb
May 2015 project update

New England Highway upgrade between Belford and the Golden Highway.

0

Reports

Show filesHide files
File Title Size
July 2018 submissions report

New England Highway upgrade between Belford and the Golden Highway.

74.5Mb
July 2018 submissions report

Submissions report appendices

15.99Mb
June 2017 review of environmental factors report

Main report.

33.1Mb
June 2017 review of environmental factors report

Appendix B - Community consultation.

3.17Mb
June 2017 review of environmental factors report

Appendix E - Biodiversity assessment report.

14.7Mb
June 2017 review of environmental factors report

Appendix G - Contamination report.

7.84Mb
June 2017 review of environmental factors report

Appendix H - Noise and vibration assessment report.

17.1Mb
June 2017 review of environmental factors report

Appendix I - Non-Aboriginal heritage assessment report

6.03Mb
June 2017 review of environmental factors report

Appendix J - Landscape Character, Visual Impact Assessment + Urban Design Study

14.3Mb
June 2017 review of environmental factors report

Appendix K - Air quality searches

200Kb
June 2017 review of environmental factors report

Appendix L - Socio-economic assessment report

2.3Mb
June 2017 review of environmental factors report

Appendix M - Climate Projections

1.11Mb
August 2015 community consultation report

New England Highway upgrade between Belford and the Golden Highway.

3.1Mb

Media releases

Show filesHide files
File Title Size
15 June 2021

Contract awarded to upgrade Golden and New England Highways

49.8Kb
3 October 2019

Upgrade for New England Highway betweeen Belford and The Golden Highway

24.3Kb

 

Reports available upon request

The following reports area available upon request by contacting us:

  • June 2017 review of environmental factors report - Appendix C - Aboriginal community consultation
  • June 2017 review of environmental factors report - Appendix D - Stage 2 walkover report
  • June 2017 review of environmental factors report - Appendix F - Cultural heritage assessment report.

Contact us

For further information or to make a complaint about this project contact:

Phone: 1800 945 202 (business hours – Natasha Waeger, Project Manager)

Email: BelfordtoGoldenHighway@rms.nsw.gov.au

Mail: Transport for NSW, Locked Bag 2030 Newcastle NSW 2300.

Complaints will be investigated within one working day from when they are received. If not already addressed via follow-up face-to-face conversation, phone call or email, a detailed response will be provided once the complaint has been investigated.

Share this page: