The experience of being on the deck of the Sydney Harbour Bridge is now more accessible with lifts to the bridge’s walkway now operational.
Project information
The Sydney Harbour Bridge Access Lifts are now open and operational 24 hours a day.
We are still working at The Rocks site to complete landscaping and refurbishment work of the City of Sydney building on Cumberland Street next to the new lift. Work at the northern lift has now been completed.
Roads and Maritime Services has installed lifts to the Sydney Harbour Bridge pedestrian walkway at Kirribilli and The Rocks to ensure everybody can enjoy the experience of being on one of Australia’s most recognisable landmarks.
Roads and Maritime Services carried out extensive work to investigate preferred locations for the lift access, taking into account the heritage value, accessibility standards, visual impacts and integration with the existing structure.
Construction of the new lifts was completed between March 2018 and December 2018.
Work to build the new lifts involved:
- setting up site compounds and installing construction signage
- removing part of the City of Sydney building at 7 Cumberland Street, The Rocks and landscaping the area
- removing two trees on Cumberland Street, The Rocks
- installing one lift on Broughton Street, Kirribilli
- installing one lift on Cumberland Street, The Rocks
- building new platforms to connect the lifts to the existing walkway
- removing and relocating existing utilities
- removing and replacing 300 metres of asphalt and adjusting the stormwater system at the southern end of the Sydney Harbour Bridge pedestrian walkway
The Review of Environmental Factors was on display for public feedback in November 2017. Roads and Maritime has prepared a report responding to all of the issues raised in the submissions received.
View or download the Submissions Report.
Artist's impression of the proposed lift at Cumberland St, The Rocks.
Artist's impression of the proposed lift at Broughton St, Kirribilli.
Project documents
Project updates
File | Title | Size |
---|---|---|
September 2018 project update
Sydney Harbour Bridge Access Lifts. |
446Kb | |
June 2018 project update
Sydney Harbour Bridge Access Lifts. |
429Kb | |
October 2017 project update
Sydney Harbour Bridge access lifts. |
522Kb |
Project notifications
File | Title | Size |
---|---|---|
June 2018 project notification
Sydney Harbour Bridge Access Lifts - new night work schedule. |
172Kb | |
May 2018 project notification
Sydney Harbour Bridge Access Lifts – temporary access changes on the walkway. |
313Kb | |
March 2018 project notification
Sydney Harbour Bridge – work starting on the Access Lifts. |
280Kb |
Construction updates
File | Title | Size |
---|---|---|
October 2018 fortnightly update
Fortnightly update from Sunday 21 October 2018. |
285Kb | |
October 2018 fortnightly update
Fortnightly update from Sunday 7 October 2018. |
315Kb | |
September 2018 fortnightly update
Fortnightly update from Sunday 23 September 2018. |
526Kb | |
September 2018 fortnightly update
Fortnightly update from Sunday 9 September 2018. |
267Kb | |
August 2018 fortnightly update
Fortnightly update from Sunday 26 August 2018. |
60.4Kb | |
August 2018 fortnightly update
Fortnightly update from Sunday 12 August 2018. |
283Kb | |
July 2018 fortnightly update
Fortnightly update from Sunday 29 July 2018. |
340Kb |
Reports
File | Title | Size |
---|---|---|
June 2018 addendum review of environmental factors report
Sydney Harbour Bridge Step Free Access. |
9.09Mb | |
December 2017 submissions report
Sydney Harbour Bridge Step Free Access. |
1.03Mb | |
October 2017 review of environmental factors report
Sydney Harbour Bridge Step Free Access. |
50.9Mb |
Media releases
File | Title | Size |
---|---|---|
October 2018 - Lift Off!! Sydney Harbour Bridge enjoys another milestone | 24.01Kb |
Contact us
Please contact the Sydney Harbour Bridge Project Team
Phone: 1800 581 595