Mount Ousley interchange

Transport for NSW is planning for an interchange on the M1 Princes Motorway at the base of Mount Ousley. The interchange will replace the existing intersection of the Princes Motorway and Mount Ousley Road, which currently experiences long queues and delays during peak periods.

Latest news

JUN 2021

JUN 2021Mount Ousley interchange progresses

The Australian Government has committed $240 million and the NSW Government has committed $60 million to build the Mount Ousley interchange.

The NSW Government has also committed $21 million for preparation work including detailed design, utility service investigations, further environmental assessment and property acquisition.

The interchange will replace the existing intersection of the Princes Motorway and Mount Ousley Road, which currently experiences long queues and delays during peak periods.

This project will improve safety for both light and heavy vehicles, provide for future traffic growth, improve access and travel time to and from the Princes Motorway and the Wollongong CBD and increase safety for both light and heavy vehicles.

The community will be kept informed of progress.

Project information

This project which will improve road safety, travel times and cater for the efficient movement of future traffic and freight growth.

Timing and funding for construction of the interchange upgrade is not yet confirmed.

The proposed interchange would replace the existing intersection, and improve safety, reduce traffic congestion and provide for future traffic growth.

In response to ongoing consultation and investigations, we have continued to improve the design of the proposed interchange.

  • new northbound exit from the motorway
  • additional heavy vehicle safety ramp
  • finalised commuter car park location with additional parking spaces and improved access
  • extended pedestrian and cyclist connections
  • relocation of the southbound entry to the motorway
  • new service road between Mount Ousley Road and University Avenue
  • closure of the southbound University Avenue exit from the motorway. Motorists would use the Mount Ousley Road exit and the service road.
  • improved travel times
  • safer access to and from the motorway to Mount Ousley Road
  • improved access to the Wollongong CBD and University of Wollongong
  • improved safety by separating cars and heavy vehicles travelling down Mount Ousley
  • improved amenity for pedestrians and cyclists
  • reduced vehicle operating costs
  • provides for future traffic growth.

Roads and Maritime displayed the Review of Environmental Factors and concept design for the Mount Ousley interchange between Thursday 16 November and Friday 15 December 2017. During the display period we received 130 submissions and a total of 236 separate comments. Read what the community had to say on the online tool.

The environmental assessment for the Mount Ousley Interchange is now complete and the Submissions Report has now been published. The report answers questions raised by the community during the consultation period last year and has proposed a few design changes. It also considers additional consultation that took place around noise management during and after construction.

Project timeline illustration

Project flowchart

  1. Preliminary investigations
  2. Refinement and analysis of options
  3. Select preferred options
  4. Concept design and environmental impact assessment
  5. WE ARE HERE
  6. Detailed design
  7. Pre-construction activities
  8. Award tender
  9. Construction


 

Project documents

Community updates

Show filesHide files
File Title Size
November 2017 community update

Mount Ousley interchange - Have your say.

1.24Mb
June 2016 community update

M1 Princes Motorway Interchange at the base of Mount Ousley.

3.54Mb

Media releases

Show filesHide files
File Title Size
21 June 2021

$60 million budget boost for Mount Ousley

48.2Kb
30 November 2020

$21 million for Mount Ousley Interchange

24.6Kb

 

Contact us

For further information about this project contact:

Email: southprojects@transport.nsw.gov.au

Mail: Mount Ousley interchange, PO Box 477 Wollongong NSW 2520.

Share this page: