The New South Wales Government is funding a major project to repaint Martin Bridge.
Latest news
MAY 2022Night work on Martin Bridge
We will be carrying out limited night work as part of the repainting project. Martin Bridge will remain open to traffic throughout the work with traffic reduced to one lane.
More informationWe will be working from Sunday 29 May for two weeks, weather permitting. We will be working from Sunday to Thursday between 7pm and 5am.
See the May 2022 project notification (PDF, 186Kb) for more information.
Due to weather delays and continuing COVID-19 impacts on the work force, we are experiencing delays to completion of the repainting project. Work on Martin Bridge is now expected to be completed by the third quarter of 2022.
We thank you for your patience.
Project information
Martin Bridge is a steel truss bridge that spans the Manning River at Taree. The bridge has an overall length of 475 metres with 15 spans, 11 of which are steel trusses. The bridge was opened in 1940 and replaced a ferry service at the end of Pulteney Street, Taree.
Transport for NSW will deliver the project which includes repairing and repainting the existing steel on the bridge. The scope of work involves encapsulating each span to remove and dispose of existing paint and apply three coats of new paint. Each span will take up to two months to complete.
Martin Bridge is a significant bridge located over an important waterway. Transport has worked closely with our contractors to develop a way to deliver the work to minimise impacts on the Manning River and the local environment.
We are making sure we minimise impacts on the local community and road users by delivering the project with very limited night work and minimal short bridge closures. Work on the project started on 11 June. Due to weather delays and continuing COVID-19 impacts on the work force, we are expecting delays to completion of the repainting project.We are currently considering alternative delivery options for the remaining work and will continue to keep the community closely informed on next steps and timing for finalising the project. We thank you for your patience.
Access will be available across the bridge during most work activities. Most of the repainting work will be carried out during the day with minor disruption to motorists and pedestrians. However full bridge closures may be required for up 15 minutes on limited occasions during the night, to facilitate isolated plant or equipment movements. These will be managed to minimise traffic disruptions and avoid the need for detours. We will advise the community in advance of these short bridge closures.
Transport for NSW will continue to keep the community advised as this project progresses.
Project documents
Community updates
File | Title | Size |
---|---|---|
May 2022 project notification
Continued out of hours work on Martin Bridge, Taree, from Sunday 29 May. |
186Kb | |
April 2022 project notification
Continued out of hours work on Martin Bridge, Taree in April and May. |
182Kb | |
March 2022 project notification
Continued out of hours work on Martin Bridge, Taree from Sunday 13 March. |
103Kb | |
February 2022 project notification
Continued out of hours work on Martin Bridge, Taree from Sunday 13 February. |
98.9Kb | |
December 2021 project notification
Out of hours work on Martin Bridge, Taree from Sunday 9 January |
93.2Kb | |
November 2021 project notification
Out of hours work on Martin Bridge, Taree from Sunday 5 December. |
151Kb | |
October 2021 project notification
Out of hours work on Martin Bridge, Taree from Sunday 7 November. |
95.9Kb | |
September 2021 project notification
Out of hours work on Martin Bridge, Taree from Sunday 10 October. |
149Kb | |
August 2021 project notification
Out of hours work on Martin Bridge, Taree from Sunday 5 September. |
150Kb | |
July 2021 project notification
Out of hours work on Martin Bridge, Taree from Sunday 8 August. |
150Kb | |
June 2021 project notification
Out of hours work on Martin Bridge, Taree in July. |
148Kb | |
May 2021 project notification
Out of hours work on Martin Bridge, Taree from Sunday 6 June |
155Kb | |
January 2021 project notification
Out of hours work on Martin Bridge, Taree in January and February 2021 |
144Kb | |
November 2020 project notification
Night work on Martin bridge |
30.9Kb | |
July 2020 project notification
Temporary closure and detour arrangements on River Street, Taree from Monday 27 July. |
245Kb | |
May 2020 project notification
Start of work on Martin Bridge, Taree from Monday 18 May. |
85.4Kb | |
May 2018 project notification
Night closures and detour arrangements on Martin Bridge, Taree from Sunday 10 June. |
138Kb | |
October 2015 project notification | 228Kb | |
July 2015 project notification | 188Kb | |
June 2015 community update | 121Kb | |
March 2014 community update | 176Kb | |
November 2013 community update | 192Kb |
Contact us
For further information about this project contact:
Phone: 02 8874 6324
Email: Jeff.moore@transport.nsw.gov.au
Mail:Transport for New South Wales, Locked Bag 2030, Newcastle NSW 2300