Hill Road Upgrade

Transport for NSW is continuing planning of proposed upgrades to Hill Road at Sydney Olympic Park and Lidcombe to improve connectivity to Carter Street Precinct and Sydney Olympic Park.

Latest news

JUL 2022

JUL 2022Investigation work on Hill Road and Parramatta Road

Transport for NSW will carry out further investigation work on Parramatta Road and Hill Road between Sunday 24 July and Thursday 8 September 2022.

Work will be carried out in these areas:

  • Parramatta Road between Bombay Street and Frances Street, Lidcombe
  • M4 Motorway eastbound and westbound on and off ramps and westbound on ramp at Hill Road, Sydney Olympic Park and Lidcombe
  • Hill Road and Carter Street and John Ian Wing Parade intersections, Sydney Olympic Park.

The work will take up to 30 night shifts between Sunday 24 July and Thursday 8 September 2022, weather permitting.

Our work hours will be between 9pm and 5am from Sunday to Thursday.

We will be on site for up to five nights a week. We will not work on Saturdays.

For more information, you may view or download the July 2022 community notification (PDF, 302Kb).

MAY 2022

MAY 2022Investigation work on Hill Road and Parramatta Road

Transport for NSW will carry out investigation work on Parramatta Road and Hill Road between Sunday 29 May and Thursday 30 June 2022.

Work will be carried out in the below areas:

  • Parramatta Road between Bombay Street and Frances Street, Lidcombe
  • M4 Motorway eastbound and westbound on and off ramps and westbound on ramp at Hill Road, Sydney Olympic Park and Lidcombe
  • Hill Road and Carter Street and John Ian Wing Parade intersections, Sydney Olympic Park.

The work will take up to 15 night shifts between Sunday 29 May and Thursday 30 June 2022, weather permitting.

Our work hours will be between 9pm and 5am from Sunday to Thursday.

We will be on site for up to five nights a week. We will not work on Saturdays or on public holidays.

For more information, you may view or download the May 2022 investigation notification (PDF, 304Kb).

MAR 2022

MAR 2022Submissions Report now available

Transport for NSW invited public feedback in November and December of last year on the Review of Environmental Factors for proposed upgrades to Hill Road at Sydney Olympic Park and Lidcombe.

Over the consultation period we received 25 responses from the public. Transport for NSW has summarised all feedback and responses in a submissions report (PDF, 1.41Mb) which is now available for the community to view or download.

After carefully considering the feedback received, Transport for NSW has decided to proceed with the project with no changes to the proposed design, or the environmental assessment, or safeguard and management measures as described in the Review of Environmental Factors.

Transport for NSW would like to thank everyone who took the time to review the documents and provide feedback and suggestions.

Further information can be found in the March 2022 Project notification (PDF, 431Kb).

DEC 2021

DEC 2021Community consultation is now closed

Community consultation has now closed on the Review of Environmental Factors for proposed upgrades to Hill Road at Sydney Olympic Park and Lidcombe. Consultation was held from 15 November 2021 to 12 December 2021.

Transport for NSW would like to thank everyone who provided feedback during this time.

We are currently reviewing all community submissions.

Once completed a Submissions Report will be available on the project webpage.

NOV 2021

NOV 2021Have your say on the review of environmental factors

Transport for NSW is seeking community feedback on the Review of Environmental Factors (REF) for proposed upgrades to Hill Road at Sydney Olympic Park and Lidcombe.

The community is invited to provide feedback from Monday 15 November until Sunday 12 December 2021.

View or download the November 2021 project notification (PDF, 735Kb).

View or download the review of environmental factors (PDF, 25.6Mb).

Community feedback can be provided by:

  • Email: hill.road@transport.nsw.gov.au
  • Write: Hill Road upgrade project team
    Central River City, Parramatta and Cumberland
    Transport for NSW
    Level 11 130 George Street
    PARRAMATTA NSW 2150

The Project Infoline 1800 979 577 (during business hours) is also available for members of the public to make enquiries.

Community feedback will help Transport for NSW understand what is important to customers and the community.

SEP 2021

SEP 2021Community Consultation Report now available

In December 2020, Transport for NSW invited public feedback on proposed upgrades to Hill Road at Sydney Olympic Park and Lidcombe.

The six week community consultation period closed on 1 February 2021, with 31 submissions received, including formal submissions from local government, peak bodies and other professional and advocacy organisations as listed below:

  • City of Parramatta Council
  • Cumberland Council
  • Sydney Olympic Park Business Association
  • Business Western Sydney
  • Restore Inner West Line community action group

A summary of public feedback and Transport for NSW responses can be found in the September 2021 Community Consultation Report (PDF, 8.57Mb).

Transport for NSW would like to thank everyone who provided feedback.

Transport for NSW will continue to engage with the local community, local businesses and key stakeholders as the project progresses through the concept phase, through detailed design and onwards to construction.

The Review of Environmental Factors for the project will be published for public comment on Transport’s website in the fourth quarter of 2021.

APR 2021

APR 2021Investigation work on Hill Road and Parramatta Road

Transport for NSW will be carrying out investigation works on Parramatta Road and Hill Road between April and June 2021.

The Work will take place on up to 25 night shifts between 12 April and late June 2021.

For more information, you may view or download the April 2021 investigation notification (PDF, 663Kb).

FEB 2021

FEB 2021Community consultation is now closed

In December 2020, Transport for NSW invited public feedback on proposed upgrades to Hill Road at Sydney Olympic Park and Lidcombe.

The six-week community consultation period closed on 1 February 2021.

Transport for New South Wales would like to thank everyone who provided feedback.

Transport is currently reviewing all community submissions. Once completed a Consultation Report will be available on the project webpage.

DEC 2020

DEC 2020Have your say on proposed upgrades

Transport for NSW is seeking public feedback on proposed upgrades to Hill Road at Sydney Olympic Park and Lidcombe.

The proposal involves major improvements to Hill Road and Parramatta Road and Hill Road and John Ian Wing Parade intersections.

Upgrades will provide better access to Sydney Olympic Park, as well as the Carter Street Precinct. The proposed upgrades will also improve access to the neighbouring suburbs of Newington and Wentworth Point, as well as ease congestion at Parramatta Road.

For further information view or download the December 2020 Have Your Say notification (PDF, 6.2Mb).

Cancellation of the proposed M4 westbound off ramp

Transport for NSW had considered a new westbound off ramp from the M4 Western Motorway, at its intersection with Hill Road, as part of proposed Hill Road upgrades.

After further safety and environmental investigations, and consideration, it has been determined that this proposed upgrade cannot be delivered safely and is no longer being considered.

For further information view or download the December 2020 Have Your Say notification (PDF, 6.2Mb).

Project information

Over the coming years, Hill Road will form an increasingly important road link in a growing and developing part of Sydney’s Central River City.

Proposed Hill Road upgrades will support future development growth in the Carter Street Precinct, which will become home to more than 6,200 new homes, as well as a new primary school and commercial and retail properties.

Upgrades will also improve connectivity to Wentworth Point, Newington, Lidcombe, Sydney Olympic Park and access to Parramatta Road and the M4 Motorway (eastbound) off ramp to Hill Road.

Start of construction is expected to commence in 2023 and take about 18 months to complete.

For further information on the Carter Street Precinct visit the Department of Planning, Industry and Environment’s website.

Key benefits include:

  • improved road capacity to meet future traffic growth and connectivity to Carter Street Precinct
  • improved connectivity to Sydney Olympic Park, especially during major events
  • improved connectivity to the neighbouring residential suburbs of Lidcombe, Wentworth Point and Newington
  • improved traffic flow and reduced traffic congestion at Hill Road and Parramatta Road and Hill Road and John Ian Wing Parade intersections
  • improved road safety for all road users
  • reduced travel times for all future road users
  • enhanced active transport links and access to public transport.

Key features include:

  • widening and upgrading the intersection at Parramatta Road, Hill Road and Bombay Street to provide:
    • dedicated dual right turns from Hill Road into Parramatta Road (westbound)
    • new left turn lane from Parramatta Road into Hill Road (northbound)
    • additional through lane from Bombay Street into Hill Road (northbound)
    • additional right turn lane from Bombay Street into Parramatta Road (eastbound)
  • widening and signalising of the M4 Motorway (eastbound) off ramp into Hill Road to provide:
    • additional left turn lane from M4 Motorway into Hill Road (northbound), creating dual left turns
  • modifying the intersection at Hill Road and Carter Street to prohibit right turn into Carter Street from Hill Road
  • adding a new fourth approach at the intersection of Hill Road and John Ian Wing Parade to provide:
    • main access to Carter Street Precinct through the future Stockyard Boulevard (formerly referred to as Green Spine Road)
    • new dual right lanes from Stockyard Boulevard into Hill Road (northbound)
    • new through lane from Stockyard Boulevarde into John Ian Wing Parade (westbound)
    • new left lane from Stockyard Boulevard into Hill Road (southbound)
  • upgrading the intersection at Hill Road and John Ian Wing Parade to provide:
    • new left lane from Hill Road into Stockyard Boulevard (eastbound)
    • new through lane on Hill Road (southbound)
    • additional right lane from Hill Road into Stockyard Boulevard, creating dual right lanes (eastbound)
    • additional right lane from John Ian Wing Parade into Hill Road, creating dual right turns (southbound)
  • building new shared pathways for pedestrians and cyclists on the western side of Hill Road between Parramatta Road and Carter Street and on the eastern side of Hill Road between Carter Street and Stockyard Boulevard
  • widening footpaths at Hill Road and Parramatta Road and John Ian Wing Parade intersections
  • modifying the kerb on the northwest corner of Birnie Avenue and Parramatta Road intersection to improve B-double and heavy vehicle access.

The proposal received formal approval in March 2022. Transport for NSW is now finalising the detailed design of the project. Start of construction is expected to commence in 2023 and take about 18 months to complete.

We will continue to keep the community informed as the project progresses by community notifications and updates to the project webpage.

For the latest information on the Hill Road upgrade project as it continues to progress, subscribe to project updates by sending an email to hill.road@transport.nsw.gov.au.

Project notifications

Please note – documents published before November 2020 contain reference to a westbound off ramp from the M4 Western Motorway at Hill Road. This off ramp is no longer under consideration

Project documents

Project notifications

Show filesHide files
File Title Size
July 2022 project notification

Hill Road upgrade at Sydney Olympic Park and Lidcombe

302Kb
May 2022 project notification

Hill Road upgrade at Sydney Olympic Park and Lidcombe.

304Kb
March 2022 project notification

Close of consultation on ‘Have your Say’ on Review of Environmental Factors, 15 November to 12 December 2021.

431Kb
November 2021 project notification

Have your say on the review of environmental factors.

735Kb
April 2021 project notification

Investigation work on Hill Road, Parramatta Road and Birnie Avenue, Sydney Olympic Park and Lidcombe.

631Kb
December 2020 project notification

Have your say on the proposed upgrade of Hill Road, at Sydney Olympic Park and Lidcombe, December 2020.

6.2Mb
May 2017 project notification 2.51Mb
April 2017 project notification

Utility investigation work on Hill Road, Lidcombe from Monday 1 May 2017.

388Kb
February 2017 project notification

Investigation work on Hill Road, Lidcombe from Wednesday 22 February 2017.

524Kb
November 2016 project notification

Investigation work on Hill Road and Parramatta Road, Lidcombe from Wednesday 9 November 2016.

385Kb

Review of environmental factors

Show filesHide files
File Title Size
Review of environmental factors

Main report

25.6Mb
Appendix A

Hill Road concept design

1.88Mb
Appendix B

Consideration of clause 228(2) factors and matters of national environmental significance and Commonwealth land

208Kb
Appendix C

Statutory consultation checklists

164Kb
Appendix D

Biodiversity assessment report

7.1Mb
Appendix E

Flood impact assessment report

31.1Mb
Appendix F

Phase 1 contamination assessment report

19.7Mb
Appendix G

Traffic impact assessment report

5.66Mb
Appendix H

Noise and vibration assessment report

29.95Mb
Appendix I

Statement of Heritage assessment report

5.01Mb
Appendix J

Landscape character and visual impact assessment report

25.6Mb
Appendix K

Socio-economic assessment report

4.07Mb
Appendix L

Neutral or beneficial effect on water quality assessment

129Kb

Reports

Show filesHide files
File Title Size
March 2022 submissions report

Hill Road Upgrade.

1.41Mb
Hill Road community consultation report

September 2021

8.57Mb

 

Contact us

For further information please contact the project team:

Phone: 1800 979 577 (during business hours)

Email: hill.road@transport.nsw.gov.au