Barham Koondrook Bridge fit for freight

12 February 2021

Work to restore the Barham Koondrook Bridge is set to start, ensuring the bridge delivers safer journeys for the freight industry and local Murray River border communities well into the future.

Minister for Regional Transport and Roads Paul Toole said the $1.5 million project, which was postponed due to high water levels in the Murray River and the COVID-19 pandemic last year, involves repairing piers that support this rare example of a De Burgh truss bridge.

“This is one of the oldest lift span bridges along the Murray River and we want to ensure we retain its heritage value while supporting the needs of today,” Mr Toole said.

“The restoration work we’ll see kick off next week will ensure this Heritage listed bridge will continue to meet current vehicle loads and the growing needs of locals, freight and tourists. Without this work, load limits would be imposed, restricting accessibility across the river, so it’s a huge win for the freight industry.”

Member of the Legislative Council Wes Fang said repairing corrosion in the watertight metal retaining structures around the bridge’s piers would support heavy vehicle traffic travelling between Victoria and NSW through the Riverina.

“The repair of these structures, which will support 10 jobs, follows a major restoration of the bridge completed in December 2018,” Mr Fang said.

“The work will involve removing rust and paint from the damaged structure surface, applying a seal to the area and installing a new steel plate.”

Work will take place between 7am and 6pm weekdays from Monday, 15 February and is expected to take three months to complete, weather permitting. During the work, the bridge will remain open with a reduced speed limit of 20 km/h, which may result in occasional delays of up to 20 minutes.

For boaters, the lift span will remain operational and the main travel channel will stay open. There will be maritime speed limits of four knots on the Murray River during the maintenance work.

Motorists are advised to drive to the conditions, and follow the directions of signs and traffic control.